At our social housing project in North Belfast, progress continues with a new name appointed for the scheme.

Section 1 of the 1st floor apartment slab and the brickwork for the 29 houses is now complete.

With 2nd fix joinery commenced and internal plastering ongoing. Further internal works will begin on the 3 Special Requirement houses in the next weeks.

The development was also named as Galgani Crescent. This gives a nod to the site’s former use as an all-girls High School, as ‘Galgani’ is Saint Gemma’s surname.

 

2b047549 52b1 4be8 8365 67cd63be144b 300x225 - Project Update: St Gemma's Ardoyne 56f62a6d 0662 43d2 bb23 1b9e163804e1 300x225 - Project Update: St Gemma's Ardoyne ed97bf9e 6b5f 4b37 be86 6de019c480c7 300x225 - Project Update: St Gemma's Ardoyne fa21013c fa04 4eb5 99d1 e19a619e6041 300x225 - Project Update: St Gemma's Ardoyne